9.1 A
SSESSMENT
F
RAMEWORK OF
E
NERGY
P
ERFORMANCE
Copyright © BEAM Society Limited. All rights reserved. Page 131
iii.
testing and commissioning records;
CO
2
Sensors Controlling Fresh Air Rate
Credit shall be achieved where the following was provided:
i.
All air handling units and primary air handling units installed
by the Applicant and supplying outdoor air to the project
space shall be variable speed, and controlled by CO
2
sensors
capable of sensing and modulating outdoor air rate in
response to demand;
ii.
testing and commissioning records shall also indicate the CO
2
set point for maximum and minimum outdoor air;
Enthalpy Controlled Free Cooling by Host building
Credit shall be achieved where the following was provided:
i.
All air handling units, and primary air handling units installed
have the capacity to deliver 100% outdoor air to the project
space;
ii.
Enthalpy sensors shall control the delivery of outdoor air into
the
project spacedependant on the Enthalpy set points;
iii.
testing and commissioning records shall state set points;
Recommended Installation Positions For Air Conditioning Units
Credit shall be achieved where the following was provided:
i.
all air conditioning units (including indoor and outdoor units of
for split-type, VRV, VRF air-conditioning units, and window
type air conditioning units) installed by the Applicant and
serving the project space shall comply with the recommended
installation dimensions given in manufacturers installation
specification;
ii.
drawings, dimensioned 1:50 scale installation drawings
demonstrating the installation position of the air-conditioning
units installed;
iii.
Letter from the manufacturer or supplier stating that the
installation position of air-conditioning units complies with the
recommended installation dimensions;
Provision of Openable Windows
Credit shall be achieved where the following was provided:
i.
openable windows, within the project space, have a total area
not less than 1/16 of the internal floor area.
M
INIMUM
S
YSTEM
REQUIREMENTS FOR
P
RESCRIPTIVE
L
IGHTING
S
TRATEGIES
Reduction of Lighting Power Density (LPD)
Credit shall be achieved where the following was provided:
i.
calculation, the method for Lighting Power Density (LPD) shall
reference latest version of BEC. Baseline values shall also
reference the latest version of BEC;
ii.
technical data sheets for equipment;
iii.
record photographs;
Appropriate Zoning and Manual Control Distribution
Credit shall be achieved where the following were provided: