ONSTRUCTION

IAQ M

ANAGEMENT

Copyright © 2012 BEAM Society Limited. All rights reserved.

Page 149

6

IEQ

6.3

I

NDOOR

A

IR

Q

UALITY

I

EQ

5 C

ONSTRUCTION

IAQ M

ANAGEMENT

E

XCLUSIONS

Residential and similar buildings not provided with central air-

conditioning and ventilation systems.

O

BJECTIVE

Ensure that building ventilation systems are not contaminated as a result

of residuals left over from construction activities.

C

REDITS ATTAINABLE

2

P

REREQUISITES

None.

C

REDIT REQUIREMENT

a) Construction IAQ management

1 credit for implementing a Construction IAQ Management Plan.

b) Filter replacement and flush-out

1 credit for undertaking a building ‘flush out’ or ‘bake out’; and

replacement of all filters prior to occupancy.

A

SSESSMENT

a) Construction IAQ management

To demonstrate compliance, the Client shall submit a report prepared by

a suitably qualified person documenting effective implementation of a

Construction IAQ Management Plan appropriate to the scale and extent

of the development including, but not limited to, the following:

a copy of the Plan;

evidence of measures showing protection of ducts, on-site storage

or protection of installed absorptive materials, etc;

checklists, worksheets, notifications, deficiencies, resolutions, etc.,

related to construction IAQ issues;

documentation that demonstrates implementation of construction

IAQ management measures during construction;

details of filtration media used during construction and installed

immediately prior to occupancy; and

documentation for duct cleaning and testing.

Where due attention has been paid to construction IAQ management as

detailed in the checklist below, the credit shall be awarded.

b) Filter replacement and flush-out

The Client shall submit a report prepared by a suitably qualified person

detailing the technical information for the filtration media used during

construction and installed immediately prior to occupancy. The report

shall also provide the detail of building flush-out procedures including

actual dates of the flush-out.

Where it can be demonstrated that filtration media used had a Minimum

Efficiency Reporting Value (MERV) of 13 as determined by

ANSI/ASHRAE 52.2-2007[ 1 ] or equivalent performance specification,

and a flush-out with new filtration media is being carried out after the

completion of construction and prior to occupancy, the credit shall be

awarded.

The flushing duration shall be subject to calculation of the fresh air

required to attain the IAQ certification 'good' class requirement. During